湖南省第六工程有限公司长沙星沙文化中心项目模板施工方案湖南省第六工程有限公司长沙星沙文化中心项目部2013年01月12日目录一、编制依据············································1二、工程概况············································1三、模板工程材料的选用··································1四、支撑系统及模板周转材料的配备························2五、模板工艺要求和施工方法······························4六、支模架搭设构造要求·································14七、检查与验收·········································15八、质量保证措施·······································15九、工期保证措施·······································23十、安全管理···········································23十一、现场文明施工和材料节约措施·······················25十二、支模架系统计算···································27一、编制依据1、《建筑施工扣件式钢管脚手架安全技术规范》JGJ130-20112、《建筑施工安全检查标准》(JGJ59-2011)3、《建筑施工手册》2008版4、《建筑施工模板安全技术规范》(JGJ162-2008)5、《混凝土结构工程施工及验收规范》(GB50204-2011)6、本工程设计单位的建筑、结构施工图二、工程概况:拟建的长沙星