斯里兰卡阿塔纳水厂Gampaha,Attanagalla&MinuwangodaIntegratedWaterSupplyScheme雨季施工专项施工方案MethodStatementinRainySeason编制:PreparedBy:审核:ReviewedBy:批准:ApprovedBy:CMEC公司斯里兰卡阿塔纳水厂项目部Gampaha,Attanagalla&MinuwangodaIntegratedWaterSupplyScheme编制时间:2017年09月01日PreparationDate:1stSeptember,2017目录Contents第一节、编制依据01ChapterIPreparationBasis第二节、工程概况.................................................01ChapterIIProjectOverview第三节、雨季施工原则............................................04ChapterIIIConstructionPrinciplesinRainySeason第四节、施工步骤.................................................05ChapterIVConstructionProcedures第五节、雨季施工管理目标.........................................10ChapterVConstructionManagementTargetsinRainySeason第六节、雨季施工的主要部位......................................11ChapterVIMajorAreasforConstructioninRainySeason第七节、雨季施工主要技术管理措施.................................11ChapterVIIMainTechnicalMeasures7.1雨季施工管理.............................................117.1ConstructionManagementinRainySeason7.2地基与基础工程..........................................137.2FoundationandBaseWorks7.3地下防水工程............................................167.3UndergroundWaterproofEngineering7.4钢筋工程................................................177.4ReinforcementWorks7.5模板工程................................................187.5Formwork7.6混凝土工程...............................................197.6ConcreteWorks7.7机电安装工程.............................................227.7MechanicalandElectricalInstallationWorks7.8砌筑工程.................................................307.8MasonryWorks7.9装饰装修工程............................................317.9DecorationEngineering7.10脚手架工程..............................................337.10ScaffoldingWorks7.11物资及设备的堆放........................................357.11StorageforMaterialsandEquipment7.12现场临电工程............................................387.12SiteTemporaryPowerWork7.13现场排水................................................397.13SiteDrainageWorks第八节、雨季安全技术措施........................................43ChapterVIIISafetyMeasuresforConstructioninRainySeason8.1机械安全技术措施.........................................438.1SafetyMeasuresforEquipmentOperations8.2施工安全技术措施........................................448.2ConstructionTechnicalSafetyMeasures8.3消防管理措施............................................488.3FireFightingControllingMeasures8.4环境保护措施.............................................488.4EnvironmentalProtectionMeasures8.5人员安全技术保障.........................................498.5TechnicalandSafetyGuaranteeforConstructionPersonnel8.6雨季卫生防疫安全隐患及预防措施...........................508.6DiseasePreventionMeasuresandHealthProtection8.7雨季安全施工工作检查.....................................528.7SafetyConstructionSupervisingandInspection第九节、附件................................................53ChapterIXAppendix第一节、编制依据ChapterIPreparationBasis序号S/N文件名称Documentationlists文件编号FileNo.备注Remarks1《建筑工程施工现场供电安全规范》CodeforSafetyofPowerSupplyandConsumptionforConstructionSiteGB50194-20142《建筑工程施工质量验收统一标准》UnifiedStandardforConstructionQualityAc...