某钢环保搬迁炼铁项目3#2500m3高炉热风炉本体专项施工方案建设单位:部监理单位:总包单位:施工单位:批准:审核:编制:2010年11月目录一、编制依据·····················3二、工程概况····················4三、工程质量目标··················4四、组织机构····················4五、施工组织部署··················5六、施工准备及各项资源需用量计划·····76
1技术准备·················76
2现场施工准备···············76
3劳动力准备·················86
4机具准备·················86
5材料准备·················10七、施工方案····················107
1炉底制安·················107
1炉壳制作·················177
3安装·····················23八、质量保证措施·················29九、安全保证措施·················31十
施工环保措施·················33十一
网络计划···················33一、编制依据一
1工程名称*钢集团环保搬迁炼铁项目3#2500m³高炉热风炉系统工程
2编制目的、宗旨本施工方案是为*钢集团环保搬迁炼铁项目3#2500m³高炉热风炉系统工程施工而编制
指导思想是:编制时为业主着想,施工时对业主负责,竣工时让业主满意,同时在经济合理,技术可靠的前提下,保安全、保质、保量、保工期完成此工程
3编制依据本施工方案编制时依据*钢集团环保搬迁炼铁项目3#2500m³高炉热风炉本体施工图及我公司GB/T19001-20