呈贡至澄江高速公路建设项目施工总承包六工区(K14+700~K18+837.662)施工便道专项施工方案编制:审核:审批:云南建工集团有限公司呈贡至澄江高速公路建设项目经理部2013/11/25目录一、工程概况.........................................................................................................................1二、编制依据及原则.............................................................................................................41、编制依据.........................................................................................................................42、编制原则.........................................................................................................................42.1、重视前期策划,合理组织实施.....................................................................................42.2、合理布置施工现场,尽量减少主体工程的资源消耗,降低生产成本.....................52.3、统筹兼顾、永临结合、方便施工及当地群众出行.....................................................52.4、采用平行、流水施工方法和网络计划技术组织,进行有序、均衡、连续的施工.52.5、确保工程质量和施工安全的原则.................................................................................52.6、一次规划、分步实施的原则.........................................................................................5三、施工总体布署.................................................................................................................61、施工总平面布置.............................................................................................................61.1、项目部驻地.....................................................................................................................61.2、钢筋加工场.....................................................................................................................61.3、材料库房及材料堆场.....................................................................................................61.4、施工用水.........................................................................................................................71.5、施工用电.........................................................................................................................72、施工组织及任务安排.....................................................................................................72.1、施工组织.........................................................................................................................72.2、施工任务安排.................................................................................................................93、施工总体目标.................................................................................................................93.1、质量目标.........................................................................................................................93.2、进度目标.........................................................................................................................93.3、安全目标.........................................................................................................................93.4、文明施工目标...............................................................................................................104、施工准备.........................................