11编制依据.......................................12工程概况.......................................22.1工程简介....................................22.2气象特征....................................22.3线路平面及纵断面......................22.4支架现浇双线简支梁分布简况.......32.5双线简支梁构造的主要技术参数.....33施工部署.......................................43.1主要设备、人员配置计划表...........43.2工期计划....................................54施工方案.......................................54.1总体施工方案介绍........................54.2支架验算....................................64.3支架现浇简支箱梁施工工艺及施工方法...................................................64.2.1施工工艺流程........................64.2.2支架施工..............................74.2.3模板工程............................104.2.4支架预压............................104.2.5支架变形观测网...................114.2.6施工预拱度的设置................124.2.7安装支座............................134.2.8钢筋施工............................144.2.9波纹管的安装及穿束.............154.2.10保护层垫块设置...................154.2.11预埋件的埋设......................15214.2.12预埋孔道的设置...................164.2.13灌注孔的设置......................164.2.14梁体砼浇筑.........................164.2.15梁体砼养护.........................184.2.16预应力施工.........................184.2.17封锚..................................214.2.18钢侧模的过孔......................224.2.19支架的拆除.........................225桥面附属工程施工.........................235.1挡碴墙、竖墙............................235.2人行道栏杆...............................235.3桥面防水层...............................235.4综合接地..................................246质量保证措施...............................246.1质量管理组织机构......................246.2质量保证措施............................256.3重点控制措施............................296.4裂缝防治措施............................326.5入模温度控制............................337安全保证措施...............................347.1建立健全各项安全制度................347.2安全教育与培训.........................347.3注重技术安全,抓好方案论证.......347.4高空作业安全保证措施................347.5防物体打击保证措施...................357.6支架施工安全保证措施................35327.7预应力施工...............................367.8施工用电安全保证措施................377.9消防安全火灾控制保障措施..........377.10夜间施工安全保障措施...............387.11防洪安全保障措施.....................387.12防台风安全保证措施..................388雨季、夏季施工保证措施................398.1雨季施工措施............................398.2夏季施工措施............................419环境保护措施...............................429.1环境保护方案............................429.2环境保护组织机构......................429.3环境保护措施............................4310应急预案....................................4510.1应急指挥机构及职责..................4510.1.1应急领导小组组织机构..........4510.1.2应急救援队组织机构.............4510.1.3应急领导小组岗位职责..........4510.1.4应急救援队岗位职责.............4610.2雨季施工应急预案.....................4610.3防台风施工应急预案..................4710.4高空坠落应急预案.....................4810.4.1防止高处坠落事故的基本安全要求................................................4810.4.2预防高处坠落和物体打击措施.4910....