第1页共49页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第1页共49页新增竖井门式起重机安装、拆卸施工方案编制:复核:审批:中铁隧道集团有限公司南宁轨道交通3号线02标土建10工区项目部2016年4月13日第2页共49页第1页共49页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第2页共49页目录1工程概况..............................................................41.1工程设计概况.....................................................41.2施工要求.........................................................41.3技术保证条件.....................................................42编制依据..............................................................43施工计划..............................................................53.1施工进度计划.....................................................53.2施工设备及机具配置...............................................63.3劳动力计划.......................................................64施工布置及门式起重机各参数表..........................................84.1施工现场平面布置图...............................................84.2门式起重机各参数.................................................84.3现场施工环境......................................................95施工前的各项准备......................................................95.1门式起重机基础及轨道验收.........................................95.2施工现场准备....................................................106劳动力计划...........................................................106.1项目专职安全员配置..............................................106.2施工管理人员、相关作业人员配置..................................117施工工艺技术.........................................................106.1各主要部件吊装点布置............................................106.2施工作业顺序....................................................116.2.1地梁总成组装..............................................116.2.2支腿组装..................................................126.2.3架设主梁..................................................146.2.4安装主梁天车...............................................16第3页共49页第2页共49页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第3页共49页6.2.5其它部件安装................................................186.2.6门式起重机电源的接入........................................186.2.7安装过程中安全保障措施.....................................186.2.8安装后检查验收内容.........................................186.3调试运行后轨道检查..............................................196.4地锚与风绳计算及设置(临时固定支腿)............................196.4.1风绳计算...................................................196.4.2地锚计算...................................................207吊装设备及机具选型....................................................217.1吊车设备及机具选型..............................................217.2吊车选型及计算..................................................248施工安全保证措施......................................................248.1组织保障........................................................248.2安全保证措施....................................................248.3施工现场安全用电保障措施........................................268.4主要风险点表....................................................288.5设备进场验收.........................