XXXXXXXXXXXXXX学院经济适用住房B楼工程消防工程施工组织设计日期:2013年12月11日编制单位:XXXXX消防设施安装集团有限公司XX分公司目录1工程概况____________________________________________________________________31.7工程范围:_______________________________________________________________42编制依据及说明______________________________________________________________43施工部署与实施______________________________________________________________53.1施工部署_______________________________________________________________513.2施工阶段的设置_________________________________________________________53.3工程立体交叉施工的管理措施_____________________________________________54拟投入本工程的资源__________________________________________________________64.1施工管理组织机构_______________________________________________________64.2人力资源_______________________________________________________________64.3机械设备_______________________________________________________________74.4物资供应_______________________________________________________________95工艺管理____________________________________________________________________95.2编制施工方案_________________________________________________________95.3编制施工计划__________________________________________________________105.4施工技术(安全)交底__________________________________________________106专业施工方案_______________________________________________________________116.1施工方案的编制和审批程序_______________________________________________116.2设备安装施工方案_______________________________________________________136.3管道工程施工方案_______________________________________________________146.4火灾自动报警工程施工方案_______________________________________________176.5工艺流程图_____________________________________________________________226.6安装工程程序框架_______________________________________________________247施工现场部署_______________________________________________________________247.1施工用临时设施布置_____________________________________________________257.2施工用水、电措施_______________________________________________________258施工协调与配合_____________________________________________________________258.1与业主(总包单位)的协调配合_____________________________________________268.2与监理单位的协调配合___________________________________________________268.3与土建单位的配合_______________________________________________________268.4与装饰公司的配合_______________________________________________________278.5其他专业单位的配合_____________________________________________________279工期保证措施_______________________________________________________________279.1施工进度计划___________________________________________________________279.2保证工程工期措施_______________________________________________________3010质量保证措施______________________________________________________________3210.1质量目标______________________________________________________________32210.2质量管理体系(QC)小组的开展____________________________________________3210.3质量控制工作的责任划分________________________________________________3310.4工程质量保证措施______________________________________________________3410.5检验和试验过程中的质量控制____________________________________________3510.6不合格品控制及纠正、预防措施__________________________________________...