第1页共51页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第1页共51页目录第一章编制依据.............................................................................................6第二章工程概况.............................................................................................7一、工程基本情况...................................................................................7二、基坑概述..........................................................................................7三、土质概况............................................................................................-6-四、周边环境...........................................................................................-7-五、基坑围护特点...................................................................................-8-六、围护体系具体做法...........................................................................-8-第三章工程目标...........................................................................................10一、质量目标..........................................................................................-9-二、安全管理目标..................................................................................-9-三、环境管理目标..................................................................................-9-四、工期目标..........................................................................................-9-五、施工组织机构..................................................................................-10-第四章挖土施工准备...................................................................................14一、布置测量网点..................................................................................-11-二、施工监测..........................................................................................-11-三、现场道路..........................................................................................-11-四、临时用电布置..................................................................................-11-第2页共51页第1页共51页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第2页共51页五、排水系统..........................................................................................-12-六、技术准备..........................................................................................-12-七、水平与垂直运输准备.....................................................................-13-八、人员准备.........................................................................................-13-九、施工机械及劳动力配备.................................................................-14-第五章与各方面沟通、协调工作........Error:Referencesourcenotfound一、与其它施工单位及外界的协调工作.............................................-16-二、与设计单位的工作协调.................................................................-16-三、与监理单位的协调工作.................................................................-16-第六章基坑开挖施工方案...........................................................................21一、基坑总体施工顺序........................................................................-17-二、基坑施工进度计划........................................................................-17-三、施工总平面布置..................................