贵州关岭普利风电场风机基础施工工程风机基础工程冬季施工方案贵州关岭普利风电场(48.0MW)新建工程风机基础施工工程冬季专项施工方案项目地址:贵州省关岭自治县普利乡项目单位:贵州关岭国风新能源有限公司建设单位:哈尔滨九洲电气股份有限公司编制单位:中国电建集团核电工程公司贵州关岭普利风电场风机基础施工工程风机基础工程冬季施工方案目录1.编制依据......................................................................................................................................22.工程概况......................................................................................................................................23.冬季气候特点..............................................................................................................................34.冬季施工特点及难点..................................................................................................................45.冬季施工界定..............................................................................................................................56.施工准备......................................................................................................................................67.冬季施工组织机构......................................................................................................................77.1冬季施工领导小组............................................................................................................77.2小组职责............................................................................................................................77.3责任划分............................................................................................................................88.冬季施工技术方案......................................................................................................................88.1钢筋工程............................................................................................................................88.2混凝土工程........................................................................................................................98.2.1混凝土搅拌站冬期施工......................................................................................108.2.2混凝土冬期施工要求..........................................................................................108.2.3热工计算..............................................................................................................138.2.4混凝土保温..........................................................................................................158.3冬季施工施工监控体系..................................................................................................208.3.1温度监控..............................................................................................................208.3.2混凝土试件的留置..............................................................................................228.3.3其他措施..............................................................................................................239.冬季施工人员培训....................................................................................................................2310.质量保证措施...............................................................................................