南宁~良庆220kV线路南宁出口段线路改造工程项目安全文明施工二次策划书批准:审核:编写:广西博阳电力工程建设有限责任公司二○一六年三月第1页共41页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第1页共41页目录1概述···································································31.1编制目的······························································31.2编制依据······························································31.3编制和适用范围························································32工程概况···································································52.1工程所处位置··························································42.2线路路径走向··························································42.3工程相关方面及工期要求················································42.4建设规模······························································52.5绝缘子、金具··························································52.6杆塔形式及数量························································53项目创优策划·······························································63.1指导思想及创优工作具体设想············································63.2工程管理目标··························································73.3样板点工程····························································83.4项目管理组织机构······················································93.5机构部门····························································124施工管理阶段····························································124.1质量职责·····························································154.2质量管理措施··························································154.3进度控制·····························································154.4施工质量控制··························································215安全管理··································································465.1安全生产方针··············...