内蒙古黄陶勒盖煤炭有限责任公司巴彦高勒煤矿主立井井筒掘砌工程施工组织设计中煤矿山建设集团二十九工程处二0一0年六月一日目录前言·······································································1第一章工程概况························································4第二章施工准备及场地布置··········································9第三章施工方案与施工装备·········································12第四章井筒及硐室施工···············································16第五章打干井施工方案和技术措施·······························31第六章主要辅助生产系统············································33第七章劳动及计划及主要施工设备·······························42第八章施工进度计划及工期保证措施····························45第九章质量保证体系及控制措施··································49第十章工程施工检测、监控·········································57第十一章施工安全控制···············································61第十二章文明施工与环境保护······································80附表一钢丝绳选型计算说明书···