国家级产品质量监督检验与研究中心实验楼室内装饰工程(项目名称)投标文件投标人:黑龙江省高维建筑装饰工程有限公司(盖单位章)法定代表人或其委托代理人:(签字)2013年7月13日目录一、施工组织设计---------------------4二、项目管理机构--------------------40三、承诺书--------------------------66四、工程质量通病防控办法------------67五、投标人承诺----------------------68施工组织设计目录一、工程概况············································4二、施工准备············································41、施工进度计划··········································52、物资材料进场材料进场··································53、劳动力计划············································54、主要施工机械设备计划··································5三、保证工程进度的组织措施································6四、主要分部分项施工方案··································61、轻钢龙骨石膏板吊顶···································62、玻化砖铺贴············································73、乳胶漆涂刷············································84、裱糊施工·············································105、干挂玻化砖···········································136、岗岩石材铺贴·········································147、楼梯不锈钢扶手·······································158、防滑地砖施工·········································159、实木门安装···········································1610、卷材防水············································1811、PVC扣板吊顶········································1912、给排水·············································1913、洁具安装···········································1914、电气工程············································20五、保证工程质量的技术措施······························21六、各方协调配合措施····································24七、降低工程成本的技术措施······························25八、保证安全生产、文明施工技术组织措施··············26九、保证环境保护技术措施································28十、成品、半成品保护技术措施····························29十一、工程质量通病防控办法·······························30附表一拟投入本工程的主要施工设备表·················34附表二拟配备本工程的试验和检测仪器设备表···········35附表三劳动力计划表············...