三角水库建设管理工作报告南宁经济技术开发区三角水库除险加固工程建设管理工作报告核定:黄荣胜审查:罗国庆编写:梁世昌XX市XX县区康宁水库管理所二○一六年六月目录1工程概况..................................................................31.1工程位置............................................................31.2立项、初设文件批复..................................................31.3工程建设任务及设计标准..............................................41.4主要技术特征指标....................................................41.5工程主要建设内容....................................................51.6工程布置............................................................51.7工程投资............................................................61.8主要工程量和总工期..................................................62工程建设简况..............................................................62.1施工准备............................................................62.2工程施工分标情况及参建单第1页共15页位..........................................72.3工程开工报告及批复..................................................72.4主要工程开完工日期..................................................72.5主要工程施工过程....................................................72.6主要设计变更........................................................92.7重大技术问题处理....................................................93项目管理..................................................................93.1机构设置及工作情况..................................................93.2主要项目招标投标过程...............................................113.3工程概算与投资计划完成情况.........................................123.4合同管理...........................................................133.5材料及设备供应.....................................................134工程质量.................................................................144.1工程质量管理体系和质量监督.........................................144.2工程项目划分.......................................................154.3质量控制和检测.....................................................154.4质量事故处理情况...................................................15第2页共15页14.5质量等级评定.......................................................155安全生产与文明工地.......................................................166工程验收.................................................................176.1分部工程验收和完工验收.............................................176.2阶段验收...........................................................176.3专项验收.......................................................................................................................................187工程运行管理情况.........................................................187.1管理机构、人员和经费情况...........................................187.2工程移交.......................................................................................................................................188存在问题及处理意见.......................................................189工程尾工安排.............................................................1810经验与建议..............................................................181工程概况1.1工程位置三角水库枢纽位于XX市XX县区吴圩镇光明村,坝址距XX市29公里,...