拉屋新建尾矿库工程施工组织设计编制:审核:陕西省三秦建设集团总公司2012年6月8日1施工组织设计陕西省三秦建设集团总公司目录1.工程概况...................................................................................................................................-1-1.1工程概况........................................................................................................................-1-2.施工方案...................................................................................................................................-1-2.1、施工内容.......................................................................................................................-1-2.2、土方挖运施工方法.......................................................................................................-1-2.2.1、施工测量.........................................................................................................-1-2.2.2、开挖施工方法..................................................................................................-1-2.2.3、主要施工设备..................................................................................................-2-2.2.4、质量控制措施..................................................................................................-2-2.2.5、土方填筑施工方法..........................................................................................-2-2.2.6、土料的雨季施工..............................................................................................-4-2.2.7、土方填筑应注意的事项:..............................................................................-5-2.2.8、施工工艺流程..................................................................................................-5-2.3、涵洞施工方案...............................................................................................................-5-2.3.1、施工测量.........................................................................................................-5-2.3.2、涵渠施工方法..................................................................................................-5-2.3.4、施工工艺流程................................................................................................-10-2.4、拦洪坝施工.................................................................................................................-12-2.4.1、施工方法.................................................................................................................-12-2.5、主坝及侧坝、附坝.....................................................................................................-13-3、施工进度计划及保证措施....................................................................................................-15-3.1、进度安排的基本原则.................................................................................................-15-3.2、工期目标.....................................................................................................................-15-3.3、工程进度计划安排说明.............................................................................................-15-3.3.1施工总体安排.....................................................................................................-15-3.4、进度保证措施...................................................