下载后可任意编辑向莆铁路 JX-3 标轨距精调施工方案中铁五局向莆铁路 JX-3 标项目部2011 年 04 月 02 日1下载后可任意编辑向莆铁路 JX-3 标轨距精调施工方案编 制: 审 核: 审 批: 中铁五局向莆铁路 JX-3 标项目部2011 年 04 月 02 日目 录2下载后可任意编辑1 施工组织设计(方案)报审表····························12 1.编制依据及原则······································23 2.工作流程············································24 3.施工前准备··········································2 3.1钢轨轨距精调使用工具 ···································23.2人员配备 ·················································35 4.调整方法···········································4 4.1轨距调整 ·················································44.2轨距调整的步骤 ··········································46 5.轨距精调质量控制要点································63下载后可任意编辑轨距精调施工方案1、编制依据及原则 本施工方案依据《铁路轨道设计法律规范》TB10082-2024/J448-2024《客运专线铁路轨道工程施工质量验收暂行标准》铁建设【2024】160 号、向莆公司下发的关于向莆铁路轨道精调的会议纪要【2024】16 号等验收法律规范及向莆公司会议内容编制。本着保证轨距到位,为减少轨道精调后标准轨距块的富余数量,节约建设成本,确保向莆铁路工程轨距精调工作快速、高效运行。2、工作流程施 工 前 准 备 轨 道 几 何 尺 寸 测 量 整理数据 制定调整方案现场位置的确认 调 整 量确认 实施调整调整后的检查4下载后可任意编辑3、施工前准备3.1 钢轨轨距精调使用工具 每个作业面应配备工具: 1)单轨车 2 辆 2)道尺 2 把 3)塞尺 2 把 4)起道器(压机)2 台 5)撬棍 4 根6)手锤 4 把(8 磅锤) 7)Ⅲ型...