目录1施工组织设计(方案)报审表····························121
编制依据及原则······································232
工作流程············································243
施工前准备··········································23
1钢轨轨距精调使用工具···································23
2人员配备·················································354
调整方法···········································44
1轨距调整·················································44
2轨距调整的步骤··········································465
轨距精调质量控制要点································6轨距精调施工方案1、编制依据及原则本施工方案依据《铁路轨道设计规范》TB10082-2005/J448-2005《客运专线铁路轨道工程施工质量验收暂行标准》铁建设【2005】160号、向莆公司下发的关于向莆铁路轨道精调的会议纪要【2011】16号等验收规范及向莆公司会议内容编制
本着保证轨距到位,为减少轨道精调后标准轨距块的富余数量,节约建设成本,确保向莆铁路工程轨距精调工作快速、高效运行
2、工作流程施工前准备轨道几何尺寸测量整理数据、制定调整方案现场位置的确认调整量确认实施调整调整后的检查3、施工前准备3
1钢轨轨距精调使用工具每个作业面应配备工具:1)单轨车2辆2)道