黄陵矿业集团有限责任公司 2×300MW低热值资源综合利用电厂贮灰场施 工 组 织 设 计编 制: 审 核: 审 批: 编制时间: 目 录 第一章 编制依据及原则·············································2 第1节 编制依据················································2 第2节 编制原则·················································2第二章 工程概况及地质·············································3 第1节 工程概况················································3 第2节 地质资料······································`·········4第三章 施工总体部署················································6 第1节 施工组织管理机构······································6 第2节 施工原则·················································8 第3节 工程总目标··············································8 第4节 生产要素投入···········································9第四章 施工准备····················································10 第1节 施工技术准备··········································10 第2节 现场准备···············································11第五章 主要施工方法及技术措施·································12 第1节 施工测量放线··········································12 第2节 分部工程施工····························...