华山高速桥切割拆除项目施工方案石家庄中奥混凝土切割加固技术有限公司2008 年 12 月 10 日目 录一、工程概况······································································2二、服务与照管···································································2三、施工部署······································································21、项目管理机构的组建·························································22、项目管理人员配置····························································33、施工劳动力配置计划·························································34、主要施工机械、设备配置计划·············································4四、进度计划以及保证措施····················································51、计划进度安排··································································52、工期保障措施··································································5五、拆除施工方案································································6六、贝雷架的承载验算·························································11七、基础处理方案及路面承载验算··········································11八、质量保证措施······································...