-0-麻栗坡县大河底一级水电站可行性研究报告湖南中天水利水电勘察设计有限公司麻栗坡县大河底一级水电站工程可行性研究报告-1--0-麻栗坡县大河底一级水电站可行性研究报告湖南中天水利水电勘察设计有限公司湖南中天水利水电勘察设计有限公司二○一五年五月-2--1-麻栗坡县大河底一级水电站可行性研究报告湖南中天水利水电勘察设计有限公司批准:江谷良核定:王光审核:黄中秋审查:刘天林校核:周刚强编写:王光刘天林-3--2-麻栗坡县大河底一级水电站可行性研究报告湖南中天水利水电勘察设计有限公司-4--3-麻栗坡县大河底一级水电站可行性研究报告湖南中天水利水电勘察设计有限公司目录1综合说明.........................................................................................71.1绪论...................................................................................................71.2水文...................................................................................................71.3工程地质.....................................................................................91.4工程任务与规模..............................................................101.5工程布置及建筑物.......................................................101.6机电、金属结构及消防..........................................111.7施工组织设计.....................................................................111.8水库淹没处理及工程永久占地......................121.9环境保护与水土保持设计....................................131.10工程管理...............................................................................141.11劳动安全与工业卫生..............................................141.12投资估算...............................................................................15-5--4-麻栗坡县大河底一级水电站可行性研究报告湖南中天水利水电勘察设计有限公司1.13经济评价...............................................................................161.14结论及今后工作意见..............................................162水文...................................................................................................212.1自然地理..................................................................................212.2气象...............................................................................................232.3基本水文资料.....................................................................242.4径流...............................................................................................242.5设计洪水..................................................................................312.6泥砂...............................................................................................332.7取水口水位流量关系.................................................343工程地质.....................................................................................353.1工程概况..................................................................................353.2工程地质条件.....................................................................353.3结论与建议...........................................................................364工程任务与规模.................................................................384.1项目区概况...........................................................................384.2电站建设的必要性.......................................................414.3工程任务...................................................................