附录4输电线路工程施工安全管理及风险控制方案编制模板封面样式隋尔、隋阎35KV线路迁移改造工程施工安全管理及风险控制方案编制单位:1编制时间:年月日2批准(分管领导)年月日技术审核(技术部门)年月日安全审核(安全部门)年月日编写(项目总工)年月日3本方案模板系依照输变电工程施工安全管理及风险控制方案编制标准编写的,用于指导、示范各单位具体方案的编制。模板中【编制要点】是对各章节的内容提出的重点要求,是必须包含和遵守的要求。【示例】是依照某个工程实例编制的,供方案编制时参考,编写者可根据各自工程特点进行深化、细化、适应性调整。4目录1.概述·························41.1编制目的······························································41.2编制依据······························································41.3工程概况······························································42.安全目标·······················42.1安全管理目标························································42.2环境保护及水土保持目标·········································42.3文明施工目标························································43.安全管理机构及职责··················43.1保证机构······························································43.2监督机构······························································43.3安全职责······························································44.施工安全管理措施···················44.1作业人员基本条件··················································44.2安全管理制度和台帐···············································44.3施工安全方案管理··················································44.4安全生产费用管理··················································44.5作业人员行为管理··················································454.6施工安全风险························································44.7应急管理措施························································45.施工安全风险管理···················45.1施工安全风险管理措施··············································45.2施工重大风险及预控措施···········································45.2.1施工准备阶段······················································45.2.2基础施工阶段······················································4...