保利鑫城四期二标项目钢筋施工方案编制:审核:第1页共42页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第1页共42页审批:目录1.编制依据......................................................41.1概述............................................................41.2国家规范......................................................41.3施工图纸......................................................41.4国家、地方标准............................................41.5行业规程......................................................51.6文件............................................................52.工程概况......................................................62.1结构形式......................................................62.2主要结构材料详见下表...................................6第2页共42页第1页共42页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第2页共42页2.3钢筋连接方式...............................................62.4钢筋分项工程的施工特点................................73.施工部署......................................................73.1质量标准......................................................83.2施工队伍的选择............................................83.3施工进度计划...............................................83.5钢筋的采购、检验、加工................................93.6钢筋翻样......................................................94.施工准备....................................................104.1劳动力准备.................................................104.2技术准备....................................................104.3机具准备、材料检验....................................104.4钢筋材料计划..............................................105.钢筋工程的主要施工方法..............................105.1钢筋加工....................................................105.2钢筋加工质量管理........................................105.3钢筋半成品堆放与运输.................................10第3页共42页第2页共42页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第3页共42页5.4钢筋连接、搭接、锚固.................................105.5钢筋电渣压力焊施工工艺..............................105.6.钢筋保护层与钢筋代换................................105.7基础台梁、筏板、外墙插筋、内墙插筋绑扎.....105.8墙、柱插筋.................................................105.9剪力暗柱、暗梁墙体绑扎..............................105.10顶板钢筋绑扎............................................105.11楼梯钢筋绑扎............................................105.12悬挑梁钢筋绑扎.........................................106.钢筋工程质量保证措施.................................106.1.质量保证措施............................................106.2钢筋工程质量标准........................................106.3筋绑扎质量控制措施....................................106.4技术质量保证措施........................................107.安全生产、文明施工....................................10第3页共42页第4页共42页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第4页共42页1.编制依据1.1概述1.1.本工程钢筋施工方案依据业主提供的施工图;保利鑫城四期二标段施工组织设计,结合现行国家、行业相关规范、规程以及江苏省建设厅、徐州市建委的相关规定编写,编制依据如下1.2国家规范《混凝土结构工程施工质量验收规范》GB50204-2002《地下防水技术规范》GB50108-2008《砌体工程施工质量验收规范》GB50203-2011《建筑地基基础...