北京城乡世纪广场工程地下室钢筋施工方案中国新兴建设开发总公司北京城乡世纪广场项目部2012年03月12日目录一、编制依据............................................-1-1.1施工组织设计...........................................-1-1.2图纸...................................................-1-1.3主要施工标准、规范与规程...............................-1-1.4企业文件...............................................-1-二、工程概况...................................................-2-2.1工程简介................................................-2-2.2结构概况................................................-2-2.3冬期主要施工项目.......................................-3-2.4施工重点................................................-3-三、冬期施工安排...............................................-4-3.1人员组织安排............................................-4-3.2冬期施工时间、范围的确定................................-5-3.3冬期混凝土施工方法......................................-5-3.4其它相关事项安排........................................-5-四、冬期施工准备...............................................-6-4.1.技术准备...............................................-6-4.2.现场准备...............................................-7-4.3.材料准备...............................................-8-4.4.人员准备...............................................-8-五、主要项目施工方法...........................................-9-5.1土方工程................................................-9-5.2防水工程...............................................-10-5.3砌筑及抹灰工程.........................................-12-5.4钢筋工程...............................................-12-5.5模板工程...............................................-13-5.6混凝土工程.............................................-14-5.7水暖、管道工程.........................................-25-5.8外围保温...............................................-26-六、工程质量管理措施..........................................-26-七、应急措施..................................................-27-7.1凝土输送泵堵泵的预防和排除措施.........................-27-7.2施工压光人员应急准备...................................-28-7.3防碰撞应急预案.........................................-28-八、冬期安全文明施工管理措施..................................-28-8.1、防雪、防冻措施.......................................-28-8.2、防滑、防坠落措施.....................................-29-8.3、防风、防坠物措施.....................................-30-8.4、防火、消防措施.......................................-30-8.5、安全用电措施.........................................-31-8.6、冬期夜间施工安全.....................................-31-8.7、噪声污染控制.........................................-32-冬期施工现场平面布置图(附图)第1页共39页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第1页共39页北京城乡世纪广场工程冬期施工方案一、编制依据1.1施工组织设计名称编号日期城乡世纪广场施工组织设计2011.91.2图纸图纸名称图纸编号出图日期建筑施工图结构施工图1.3主要施工标准、规范与规程第2页共39页第1页共39页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第2页共39页1.4企业文件名称编号施工组织设计管理办法新建技质(2002)194号总公司施工现场文明安全管理规定内部资料二、工程概况2.1工程简介2.1.1工程位置本工程建设地点位于北京市亦庄经济开发区科创五街北侧,经海一路和二路之间,交通便利。2.1.2...