第0页共109页和玉
世纪新城(二期)基础施工专项施工方案和玉
世纪新城(二期)项目基础施工专项方案编制单位:八冶建设集团有限公司编制人:审核:编制时间:2017年7月5日目录第一节工程概况·······················61
1参建单位简介:······················6第1页共109页和玉
世纪新城(二期)基础施工专项施工方案1
2工程概况:························61
3、地形地貌························61
4、地层岩性························61
5、地质构造························61
6水文地质条件·······················61
7、不良地质现象及地质灾害················61
8、岩体基本质量等级····················6第二节编制依据及原则····················62
1、编制依据·······················102
2、编制原则·······················122
3、编制范围·······················13第三节施工计划:·····················133
1、施工进度计划(附后)·················133
2、材料计划·······················133
3、设备计划·······················14第四节主要施工工艺技术:技术参数、工艺流程、施工方法、检查验收等····························164
1、施工前的准备工作···················164
2、主要施工技术参数···················17第