锡通过江通道公路接线工程XT-NT2标水泥土双向搅拌桩施工方案编制:审核:审批:中铁大桥局集团有限公司锡通过江通道公路接线工程XT-NT2标项目经理部二○一七年一月目录第一章工程概况..........................................................11.1、工程概况...........................................................11.2、地形地貌...........................................................11.3、气候...............................................................11.4、工程地质条件.......................................................21.5、编制依据...........................................................2第二章总体施工规划......................................................42.1、施工人员组织.......................................................42.2、施工机械设备.......................................................42.3、施工材料...........................................................52.4、施工工期计划.......................................................6第三章施工方案...........................................................73.1、技术参数...........................................................73.2、水泥双向搅拌桩配合比...............................................73.3、施工方法...........................................................73.4、打桩过程质量检查..................................................113.5、桩身质量检测......................................................113.6、施工中常见问题及处理..............................................12第四章质量保证措施.....................................................134.1施工组织管理.......................................................134.2建立健全各项质量管理制度...........................................13第五章安全及环水保措施.................................................145.1安全保证措施........................................................145.2环水保措施..........................................................175.3节能减排措施........................................................17第六章绿色施工.........................................................206.1环境保护措施........................................................206.2节材与材料资源利用..................................................206.3节水与水资源利用....................................................216.4节能与能源利用......................................................216.5节地与土地保护......................................................216.6文明施工保证措施....................................................21第七章附表、附图.......................................................23附件1《水泥土双向搅拌桩施工承包协议登记表》;..........................23附件2《水泥土双向搅拌桩施工桩机登记表》;..............................23附件3《水泥土双向搅拌桩施工桩机日工作量统计台帐》;....................23附件4《水泥土双向搅拌桩水泥调拨台帐》;................................23附件5《水泥土双向搅拌桩施工现场记录表》;..............................23附件6《水泥土双向搅拌桩检测桩登记表》;................................23附件7《水泥土双向搅拌桩现场检测表》;..................................23附图1《K23+265~K23+319.3区段内水泥土双向搅拌桩编号图》。..............230锡通过江通道公路接线工程XT-NT2标水泥土双向搅拌桩施工方案第一章工程概况1.1、工程概况无锡至南通过江通道公路北接线工程XT-NT2施工标段路线长5.585km(K20+595.160~K26+180.000),路基填土为1...