中交一公局贵安新区马场科技新城商业综合体施工二标50米双排落地式脚手架施工方案中交一公局贵安新区马场科技新城商业综合体项目施工二标50米双排落地式脚手架施工方案编制:______________审核:______________批准:______________中交一公局贵安新区马场科技新城1中交一公局贵安新区马场科技新城商业综合体施工二标50米双排落地式脚手架施工方案商业综合体项目施工二标项目经理部二0一六年六月目录1工程概况-----------------------------------------------------------------------------------------1-1.1工程概况---------------------------------------------------------------------------------1-1.2施工要求---------------------------------------------------------------------------------1-1.3技术保证条件---------------------------------------------------------------------------1-2编制依据-----------------------------------------------------------------------------------------3-3施工计划-----------------------------------------------------------------------------------------4-3.1施工方案设计---------------------------------------------------------------------------4-3.2材料与设备计划------------------------------------------------------------------------4-4施工工艺技术-----------------------------------------------------------------------------------6-4.1技术参数---------------------------------------------------------------------------------6-4.2工艺流程---------------------------------------------------------------------------------6-4.3施工方法---------------------------------------------------------------------------------6-4.4检查验收--------------------------------------------------------------------------------13-5施工安全保证措施---------------------------------------------------------------------------15-5.1组织保障--------------------------------------------------------------------------------15-5.2技术措施--------------------------------------------------------------------------------17-5.3监测监控--------------------------------------------------------------------------------18-5.4应急预案--------------------------------------------------------------------------------20-6劳动力计划------------------------------------------------------------------------------------22-6.1专职安全生产管理人员--------------------------------------------------------------22-7计算书及相关图纸---------------------------------------------------------------------------23-7.1脚手架架在楼板上计算书-----------------------------------------------------------23-一、工程属性----------------------------------------------------------------------------23-二、支架搭设参数----------------------------------------------------------------------23-三、荷载参数----------------------------------------------------------------------------24-四、各楼层荷载计算-------------------------------------------------------------------25-五、板单元内力计算-------------------------------------------------------------------27-六、楼板裂缝验算----------------------------------------------------------------------30-2中交一公局贵安新区马场科技新城商业综合体施工二标50米双排落地式脚手架施工方案七、楼板抗冲切验算-------------------------------------------------------------------32-7.2钢管落地脚手架计算书--------------------------------------------------------------33-一、脚手架参数-------------------------------------------------------------------------33-二...