芦山中学至三小围墙外非机动车道、人行道暨电缆沟工程编制单位:重庆市圣奇建设(集团)有限公司编制日期:2013年2月17日目录第一章编制依据及原则··································第二章工程概况········································第三章施工组织机构····································第四章施工总平面布置··································第五章施工方案及技术措施······························第六章质量管理体系与措施······························第七章安全管理体系与措施······························第八章环境保护管理体系与措施··························第九章工程进度计划与措施······························第十章主要施工机械设备情况····························第十一章劳动力安排计划································第十二章原材料进场计划································第十三章其他应说明事项································第十四章附表··········································第一章编制依据及原则一、编制依据1、芦山中学至三小围墙外非机动车道、人行道暨电缆沟工程招标文件、设计图纸及工程量清单
2、我公司质量标准制定的质量手册及相关程序文件
3、我公司自身的人力资源和技术装备能力以及施工同类工程的施工经验
4、通过现场实地踏勘,从现场调查