1广西城建建设集团有限公司满堂式支架专项施工方案A2施工组织设计(方案)报审表致:广西大通建设监理咨询管理有限公司我方已根据施工合同有关规定完成了本工程K0+583.535中桥现浇T梁满堂式支架安全专项施工方案的编制,并经我单位上级技术负责人审查批准,请予以审查。附:K0+583.535中桥现浇T梁满堂式支架安全专项施工方案承包单位(章)广西城建建设集团有限公司项目经理日期年月日专业监理工程师审查意见:专业监理工程师日期年月日总监理工程师审查意见:项目监理机构(章)总监理工程师日期年月日21广西城建建设集团有限公司满堂式支架专项施工方案工程名称:2015年大丰生态移民B区道路基础设施设计、采购、施工(EPC)总承包项目新明路西段道路工程编号:2015年大丰生态移民B区道路基础设施设计、采购、施工(EPC)总承包项目新明路西段道路工程K0+583.535中桥现浇T梁满堂式支架安全专项施工方案编制:审核:建设单位负责人审查意见:建设单位(章)负责人日期年月日32广西城建建设集团有限公司满堂式支架专项施工方案审批:编制单位:广西城建建设集团有限公司编制时间:二零一七年十二月十五日目录第一章工程概况·······································································11.1工程概况··········································································································1第二章编制说明·······································································51.1编制依据·············································································································51.2编制原则·············································································································51.3编制范围·············································································································5第三章施工计划·······································································63.1工序所需时间分析······························································································63.2施工进度计划····································································································63.3材料计划··········································································································63.4设备计划··········································································································73.5劳动力计划······························································...