[巴岳建司美的·国宾府二期三标段工程]目录一、实测实量质量控制措施························2(一)、模板工程····································2(二)、钢筋工程····································5(三)、混凝土工程··································9(四)、填充墙体与钢筋砼构造柱·····················131[巴岳建司美的·国宾府二期三标段工程]二、实测实量检测内容及标准······················15(一)、混凝土结构工程·······························15(二)、砌筑工程····································19(三)、抹灰工程····································25三、检测平面图··································31四、数据附表····························2[巴岳建司美的·国宾府二期三标段工程]········36一、实测实量质量控制措施为确保工程施工质量,根据《建筑工程施工质量验收规范》中实测实量内容要求,特对主要检测内容在施工过程中进行重点控制,并对砼工程在现场设置上墙检查牌,主要质量过程控制如下:(一)模板工程1、轴线偏位(1)精确弹线:每层都必须从同一基准点出发测出各条轴线,并按测量的要求进行复测,校核其精度是否达到要求,严禁用丈杆逐段引测轴线,且不进行校核的办法
建筑物较长、轴线较多时,可在中间选择一二点进行复核
(2)成排的柱子宜弹出通线,并将柱子边线兜方
梁的轴线,边线宜先用墨斗在楼面上弹线,再引测到柱上,以作复核之用,防3[巴岳