PP-HM 双壁波纹管施工方案目 录一、工程概况 ............................................2二、编制依据 ............................................2三、施工资源配置 ........................................23.1 施工组织机构 ...................................... 23.2 劳动力需求计划 .................................... 3四、施工措施 ............................................34.1 施工原则 .......................................... 34.2 施工流程 .......................................... 44.3 检验计划 .......................................... 44.4.材料管理 .......................................... 54.5.测量放线 .......................................... 54.6.管沟开挖及措施 .................................... 54.7.基底处理和基础铺设 ................................ 64.8.下管 .............................................. 74.9.管道安装 .......................................... 74.10.管道附属井砌筑 ................................... 74.11.闭水实验 ......................................... 84.12.分层回填 ......................................... 9五、质量保证措施 .......................................10六、安全保证措施 .......................................11七、环境保护 ...........................................121PP-HM 双壁波纹管施工方案长沙市开福区次干道一(冯蔡路-高冲路)道路工程施工二标段 PP-HM 双壁波纹管施工方案一、工程概况长沙市开福区次干道一(冯蔡路-高冲路)道路工程施工二标段项目给排水工程中,包括钢筋混凝土管道的施工、和 PP--HM 双壁波纹管的施工。其中 PP--HM双壁波纹管包括管径为 DN300、DN400 和 DN500 的管道。其中 DN300 管道 460m,DN400 的管道 359m,DN500 的管道 616m。二、编制依据1.《建筑给排水设计规范》 GB50015-20032.《室外排水设计规范》 GB 50014-20063.《给水排水工程管道结构设计规范》 GB50332-20024.《给水排水管道工程施工及验收规范》 GB50268-20085.《城市工程管线综合规范规划规范》 GB502896.《CJJ143-2010 埋地塑料排水管道工程技术规程》7.《06MS201 市政排水管道工程及附属设施》8.《建筑地基基础工程施...