下载后可任意编辑目录一、 编制依据·······································································2二、 工程概况·······································································2三、 停工期间主要工作内容···························································2四、 停工具体工作安排及做法·························································3五、 材料周转及退场计划·····························································3六、 文明施工措施···································································4七、 人员退场·······································································5下载后可任意编辑八、 施工组织设计···································································5一、 编 制 依 据1、 本工程施工图纸 2、 7月9日建设单位下发工作联系单编号土建-10 二、 工程概况工程名称: 苏州绿地中央广场三号地块项目下载后可任意编辑工程地点: 苏州市科技城龙山路与科发路交叉口建设单位: 绿地集团苏州高新置业有限公司设计单位: 上海正轶建筑设计有限公司监理单位: 苏州相城建设监理有限公司勘察单位: 江苏省地质工