下载后可任意编辑1.0Purpose目的This procedure covers the application of all concrete coating systems applied by CELEB.本施工工艺规程法律规范所有北京九州华清防腐混凝土涂装系统的施工。2.0Scope范围This procedure will be followed in all applications.本规程应贯彻于所有施工过程中。3.0Responsibilities责任3.1The Project Manager 项目经理- Operation and management of grinding and painting works. Plan work schedules. Maintained strict conformance to clients required specifications.负责研磨和涂装作业的管理及运作工作。准备工作进度表。严格遵照客户要求的涂装系统及法律规范施工。-Liaise with Engineers, Production, Q.C. Personnel and other contractors on work schedules, job performance and implementation on quality control requirements. Exercised quality control surveillance on conformance to required specifications.下载后可任意编辑协调施工各方, 确保按质量按进度施工作业, 控制质量以符合业主的涂装系统法律规范。3.2The Supervisor 监理 - To ensure that all tests are undertaken and, in the case of witness tests the client representative is present.保证执行各项检测工作, 检测时应有客户代表在场。3.3The Forman -领班 - To ensure that all work conforms to specifications and is done in a workman like manner.保证按标准施工, 施工人员工作态度端正。4.0References标准Where referred to in this specification, the latest edition of the following specifications, standards and other documents apply.本规程参照以下标准及法律规范制定: ASTM D4227-99 ”Standard Practice for the Qualification of Coating Applicators for Application of Coatings to Concrete Surfaces”ASTM D4258-83 ”Standard Practice for Surface Cleaning Concrete for Coating”下载后可任意编辑ASTM D4259-88 ”Standard Practice for Abrading Concrete”ASTM D4261”Standard Practice for Surface Cleaning Concrete Unit Masonry for Coating” 5.0Documentation文件Daily Work Report / ...