旧变压器移位专项方案编制:审核:审批:建设单位审批:目录一、编制依据..................................................................................................................1二、工程概述..................................................................................................................1三、施工组织..................................................................................................................13.1项目组织机构...................................................................................................13.2施工人员配置...................................................................................................2四、施工设备机具配置计划..........................................................................................2五、施工技术措施..........................................................................................................35.1施工总体方案...................................................................................................35.2施工技术准备...................................................................................................35.3施工步骤...........................................................................................................3六、HSE管理措施..........................................................................................................96.1组织机构............................................................................................................96.2项目HSE方针...................................................................................................126.3项目HSE控制目标...........................................................................................126.4风险评估及削减措施......................................................................................126.5应急预案..........................................................................................................13七质量保证措施...........................................................................................................257.1质量目标.........................................................................................................257.2质量保证措施..................................................................................................257.3现场质检人员及职责.....................................................................................267.4质量管理的措施.............................................................................................271旧变压器移位专项方案一、编制依据1.1国家及行业现行有关施工及验收规范1.1.1《液压推杆推移主变就位工法》Q/AEPC.J02GF-4-20091.1.2《起重机吊装工和指挥人员的培训》GB/T23721-20091.1.3《机动车运行安全技术条件》GB7258—2012;1.2现场技术交底二、工程概述主要工作量为拆除原有1#、2#主变及安装新变压器附件,新变压器由厂家负责就位。1#、2#主变采用推移就位的方式进行整体移动至平板车,由平板车拉运至供电服务中心。三、施工组织3.1项目组织机构为了安全、优质、按时的完成电站变压器设备拆除任务,该工程实行项目管理由项目经理对该工程的各项经济技术指标全面负责。3.2施工人员配置序号工种数量要求备注1起重工4持证上岗主变压器推移全过程起重作业。2电工2持证上岗液压千斤顶、液压推杆、液压夹轨钳电气控制系统的现场安装、调试;3钳工2持证上岗液压推杆及液压夹轨钳的安装、调试;推移过程中的液压推杆及液压夹轨钳的泵站操作四、施工设备机具配置计...