BASF MDI Complex Chongqing ProjectMulti Discipline Construction The Third Chemical EngineeringContract No: CO-CQ5522-92L-012 Construction Company of China Rev
03, 25
2013 File No: MDI-TCC-92L012-MS-039 Page 1 of 11 Project Quality Management Preheating and Post Welding Heat Treatment Procedu re 焊前预热与焊后热处理方案 Preheating and Post Welding Heat Treatment Procedure MDI-TCC-92L012-MS-039 3 25
2013 Revised asTMDI comments 2 18
2013 Revised asTMDI comments GAO BIN XIA KAO FEI ZHAO QI 1 8,Mar,2013 Revised asTMDI comments GAO BIN XIA KAO FEI ZHAO QI 0 14,Jan,2013 Issue for approval GAO BIN XIA KAO FEI ZHAO QI Revision Date Revision Description Prepared By Reviewed By Approved By BASF MDI Complex Chongqing ProjectMulti Discipline Construction The Third Chemical EngineeringContract No: CO-