C onstruction P lan 施工方案Construction Plan施工方案Section 1.0 Plasterboard Partition on Metal Stud第一节 轻钢龙骨隔断施工方案1.1 Requirement of Materials, Components and Fittings材料及构配件要求Each kind of stud, fittings and surface materials should accord with the current requirement. Re-testing will be conducted when more than 500 square meters man-made boards are used. Provide test report of TVOC and formaldehyde for water-based adhesive.各类龙骨,配件和罩面材料及胶粘剂的材质应符合现行要求.人造板材使用量大于 500 平米时应进行复检;水性胶粘剂必须有TVOC 和甲醛检测报告。Filled with insulation material: The glass wool, rock wool, etc。 should be consistent with the design requirements填充隔音材料:玻璃棉,岩棉等应符合设计要求。1。2 Main Equipment and Tools主要机具Electrical machine & tools: Electrical saw, Hand-held electric drill, impacting drill, DC welding machine, and cutting machine电动机具:电锯,手电钻,冲击电钻,直流电焊机,切割机。Manual tool: manual saw, pliers, riveter, screwdriver, level and steel level手动工具:手锯,钳子,拉铆钳,螺丝刀,靠尺,钢水平尺.1.3 Metal Stud Installation龙骨安装The type , size , color of the materials and the structure fixing method of the partition should comply with the design. 隔断工程应用材料的品种、规格、颜色以及隔断的构造固定方法应符合设 计要求.As per the drawings, setting lines on the cleaned floor for the wall locating and drawing out the locations of doors , windows and preformed openings。按图纸要求,在清洁洁净的地面上放墙位线定位,并标出门、窗及预留孔位置,确定墙体位置Install the top and bottom studs at the wall location, screws shall be used to fix the studs and the space between screws is 600mm.在墙体位置上安装沿地、沿顶龙骨,固定龙骨采纳螺钉固定,螺钉间距为 600mm。The vertical studs will be installed into the top ...