水轮发电机定子绝缘缺陷现场修复工艺(On site repair technology of stator insulation fault of Hydrogenerator)水轮发电机定子绝缘缺陷现场修复工艺(On site repair technology of stator insulation fault of Hydrogenerator) Northwest power plant installed 3 * 6300kW, generator rated voltage 6
The first phase of 2 x 6300kW was put into operation in 1992, and the second phase of the project was installed with 1 x 6300kW in
The 3 units are vertical shaft mixed flow turbine generator sets
The first phase of the project installation and commissioning is very smooth, the second phase of the project found in the installation and commissioning of the generator stator has a major quality defects, after the site repair qualified before commissioning power generation
First, the phenomenon of failure The generator stator in March 26, by