高架桥系梁施工技术交底

高架桥系梁施工技术交底_第1页
1/7
高架桥系梁施工技术交底_第2页
2/7
高架桥系梁施工技术交底_第3页
3/7
湖南省浏阳至醴陵高速公路第十三合同段毛连湾高架桥(K80+640)系梁施工技术交底浙江八咏公路工程有限公司二 0 一 0 年七月制墩号桩顶(系梁顶)标高系梁高(m)锁口标高设计桩底标高桩长(锁口到设计桩底)(m)0-078.2040-178.2040-278.4290-378.4291-01.668.1001-11.668.1001-268.1001-368.1002-01.663.1002-11.663.1002-284.6001.684.97263.10021.8722-384.6001.684.86363.10021.8723-085.6001.686.13566.10021.8723-185.6001.685.54166.10021.8723-284.9001.685.44166.10021.8723-384.9001.685.12566.10021.8724-086.3001.687.80866.30021.8724-186.3001.686.04166.30021.8724-285.8001.686.12066.30021.8724-385.8001.685.83666.30021.8725-086.2001.687.86466.70021.8725-186.2001.686.00566.70021.8725-284.7001.685.84066.70021.8725-384.7001.685.88366.70021.8726-089.7001.689.90170.70021.8726-189.7001.689.96470.70021.8726-285.7001.688.32765.70021.8726-385.7001.685.93665.70021.8727-091.1001.692.90270.10021.8727-191.1001.690.55570.10021.8727-288.1001.690.42664.10021.8727-388.1001.688.12664.10021.872毛连湾高架桥底系梁施工技术交底毛连湾高架桥桩基已灌注 24 根。底系梁施工即将全面展开。为保证底系梁的施工质量。将对桥梁施工队进行如下交底。一、 工程概况毛连湾高架桥整体线性处于 R=2400m 的圆曲线上,底系梁分左、右幅径向布置。设计底系梁共 13 处。与设计代表协商 1-2~1-3 的底系梁取消,改为桩柱一体。其中,1-2 作接桩处理。按桥柱尺寸施工。由于毛连湾桥系梁高程变更,今将底系梁的顶、底面高程列出。详细见表一。二、 施工工艺流程测量放线 施工石线 机械开挖基坑 人工清底 5cm石渣垫层 10#砂浆铺底浇筑 破桩头测量放样(桩中心点) 放出中心线、模板安装边线 安装钢筋 安装定型模板 检查验收钢筋、模板 浇筑砼 拆模养护 验收三、 主要工序施工要求1、基坑开挖本工序主要是机械施工,配合人工清底。基坑开挖一定要在底系梁边线外加宽一边最少 1m,另一边最少宽 1.8m,保证模板安装的工作面。在基坑周围开挖排水坑有集水井,保证基坑不积水。人工清底要低于设计高程 0.1m,15#素砼封底找平。用墨斗弹出中心线、模板内边线。2、破桩头本工序主要用风镐机将设计高程以上超高部分的砼凿除。桩头周边凿到设计高程,中间部份高出 2-3cm。用水将桩基上面冲洗洁净。测量放出...

1、当您付费下载文档后,您只拥有了使用权限,并不意味着购买了版权,文档只能用于自身使用,不得用于其他商业用途(如 [转卖]进行直接盈利或[编辑后售卖]进行间接盈利)。
2、本站所有内容均由合作方或网友上传,本站不对文档的完整性、权威性及其观点立场正确性做任何保证或承诺!文档内容仅供研究参考,付费前请自行鉴别。
3、如文档内容存在违规,或者侵犯商业秘密、侵犯著作权等,请点击“违规举报”。

碎片内容

高架桥系梁施工技术交底

确认删除?
VIP
微信客服
  • 扫码咨询
会员Q群
  • 会员专属群点击这里加入QQ群
客服邮箱
回到顶部