***国际新城(***公园)钢筋工程施工方案四川***建筑工程有限公司成都***国际新城(***公园)钢筋工程施工方案编 制 人: 审 核 人: 编制单位: 编制日期: 目 录第一章编制依据···········································4第二章工程概况···········································4-5第三章施工准备···········································5-8第四章钢筋加工工程·······································8-12第五章钢筋焊接··········································12-16第六章施工工艺流程及要求································16-19第七章质量标准··········································19-20第八章成品保护措施······································20-21第九章安全文明施工措施··································21-22第十章环境保护措施······································22第一章编制依据:1.《混凝土工程施工及验收法律规范》(GB50204-2025)2. 《混凝土结构施工图》(03G101-1)3.《钢筋焊接及验收规程》(JGJ107-2025)4.《钢筋机械连接通用技术规程》(JGJ107-1996)5. 《冷扎带肋钢筋混凝土结构技术规程》(JGJ95-2025)6. 《建筑抗震设计法律规范》(GB50011-2001)9. 甲方提供的施工图纸10.《施工组织设计》第二章 工程概况 工程总体简介 表 2-1序号项 目内 容1工程名称成都***国际新城(***公园)2工程地址3建设单位4设计单位5监理单位6监督单位表 2-2序号项 目内 容备 注1总建筑面积 约 18 万平方米2结构形式框架剪力墙结构3抗震等级工程设防烈度 7 度抗震等级三级5钢筋接头形式闪光对焊 电渣压力焊直径≥12 的二级、三级钢筋搭接绑扎墙、板中直径<12 的钢筋第三章 施工准备1 材料准备:1.1 钢筋必须有出厂合格证、试验报告单,并且合格证必须随钢筋一同到场,详细内容需经试验员、钢筋技术员验证合格;钢筋力学性能复试报告;钢筋表面或每...