泥水平衡顶管技术在乙烯管廊工程中的应用讨论泥水平衡顶管技术在乙烯管廊工程中的应用讨论 摘 要:本论文在借鉴国内外泥水平衡顶管施工技术及工艺流程的基础上,根据武汉地区特别是靠近长江特有的地质条件,总结提炼了泥水平衡式顶管的施工技术及工艺要点。结合武汉石化乙烯管廊工程大型泥水平衡顶管施工的背景,总结出了一套较为科学合理的顶管施工技术方法。由实际施工情况及监测结果分析可以看出,泥水平衡顶管技术在武汉及中西部地区有一定的推广应用价值。 关键词:顶管施工;泥水平衡法;施工管理;效果监测 Abstract: in this paper, on the basis of domestic and foreign of slurry balanced pipe jacking construction technology and process, according to the particular geological conditions in Wuhan area near the Yangtze River characteristic, summarize the construction technology and key technology of slurry balance pipe jacking. Combined with the background of Wuhan Petrochemical Ethylene tube tunnel large slurry balance pipe jacking construction, summed up a set of more scientific and reasonable technique of pipe jacking construction method. By the actual construction situation and the analysis of monitoring results can be seen, slurry balance pipe jacking technology has a certain application value in Wuhan and the central and Western regions. Keywords: pipe jacking construction; the water balance method; construction management; effect monitoring 中图分类号:Q946.885+.7 文献标识码:A 文章编号:2095-2104(2025) 一、工程概况 80 万吨乙烯上游管廊工程作为中国石化武汉分公司 80 万吨/年乙烯工程项目的组成部分之一,主要承担武汉石化与乙烯工程之间物料互送任务。由武汉石化、武钢和乙烯工程所处的地理位置决定了上游管廊必须从武钢厂区通过。物料输送线包括 7 根为武汉石化和武汉乙烯之间物料输送线,1 根乙烯分输站至武汉石化天然气输送线,8 根预留管线,管径均为 250mm,介质为氢气、氮气、芳烃抽余液等物质。这些管线需要从武汉石化铺设到 80 万吨乙烯项目部,如何铺设,如何处理将直接影响工程的成败...