沈阳万科城九期工程冬期施工方案建设单位:沈阳万科永达房地产开发有限公司工程名称:万科城九期施工总承包工程施工单位:沈阳天北建筑安装工程公司第十二分公司项目经理:技术负责:安全负责:编制人:编制单位:沈阳天北十二分万科城九期项目部编制日期:2011年10月12日沈阳天北第十二分公司万科城九期项目部沈阳万科城九期地下室工程冬期施工方案会签栏单位:沈阳天北建筑安装工程公司第十二分公司工程名称万科城九期方案名称地下室冬期施工方案施工日期2011.10工程负责人唐钟声编制日期2011.10.8编制人兰华葛贤杰项目经理意见年月日签章技术负责人意见年月日签章安全负责人意见年月日签章建设单位意见年月日签章监理单位意见年月日签章目录一、编制依据······················································3二、工程概况及冬施原因············································3三、冬期施工规定··················································4四、施工特点及难点················································4四、人员组织准备··················································5六、总体安排······················································8七、钢筋工程······················································8八、模板工程······················································11九、混凝土工程····················································11十、热工计算······················································15十一、防水工程····················································16十二、冬期施工各项技术及安全保证措施······························16十三、工程越冬维护···············································20十四、冬期施工应急预案············································22十五、编后语······················································31一、编制依据:1、沈阳万科城九期工程建设单位节点要求。2、人防工程施工及验收规范(GB50134-2024)3、人民防空地下室设计规范(GB50038-2005)4、地下室防水工程质量验收规范(GB50208-2002)5、人民防空工程质量验收评定标准(RFJ01-2002)6、地基与基础工程施工及验收规范(GB50202-2002)7、建筑施工安全检查标准(JGJ59-99)8、防空地下室建筑设计(FJ01-04)9、防空地下室结构设计(FG01-03)10、钢筋混凝土双扇防护密闭门、密闭门和门框墙图集(93RFM-13)11、钢筋混凝土单扇活门槛防护密闭门、密闭门图集(97RFM)12、砼结构工程施工质量验收规范(GB50204—2002)13、建筑工程冬期施工规程(JGJ104—97)14、砼外加剂应用技术规范(GBJ119)15、辽宁省沈阳市行业管理部门关于冬期施工有关文件规定和通知。16、建筑施工手册有关冬期施工章节和冬期施工有关技术资料。17、沈阳市近年气象气温统计数据资料。18、施工现场实际情况。二、工程概况及东施原因:(1)沈阳万科城九期工程位于沈阳市和平区长白14号街,占地面积约为12000平方米,迄今为止土方开挖至-3.3米,因目前未见施工图纸,其它工程指标只能预测。(2)根据建设单位工程管理部意见和对...