目录一、编制依据..........................................................................................3二、工程概况..........................................................................................4三、施工安排..........................................................................................53.1、成立安全防护领导小组..................................................................53.2、劳动组织...........................................................................................53.3、脚手架搭设方案的总体思路...........................................................6四、施工准备..........................................................................................74.1、材料要求...........................................................................................74.2、材料准备.........................................................................................104.3、技术准备.........................................................................................104.4、生产准备.........................................................................................11五、主要施工方法................................................................................125.1、脚手架设计要求.............................................................................125.2、悬挑脚手架施工方法.....................................................................135.3、脚手架顶端构造.............................................................................215.4、搭设钢管脚手架构造要求.............................................................215.5、钢管脚手架拆除.............................................................................27六、脚手架的检查与验收......................................................................29七、质量保证措施..................................................................................31八、安全技术措施..................................................................................33九、应急预案..........................................................................................359.1应急救援指挥小组............................................................................359.2、应急知识培训.................................................................................369.3、应急预案措施的演练.....................................................................369.4、事故报告制度.................................................................................379.5、脚手架坍塌事故预案.....................................................................389.6、对外联系方式:................................................................................38十、脚手架计算......................................................................................3910.1、悬挑式双排脚手架的设计计算...................................................39十一、架体的基本形式(见外防护架立面示意图)..........................57十二、悬挑脚手架补充方案..................................................................59T8商务综合楼等7项悬挑脚手架搭拆专项施工方案一、编制依据序号名称标准号(备注)1T8商务综合楼等7项工程设计图纸2014-0762T8商务综合楼等7项工程施工组织设计C1-0013建筑施工高处作业安全技术规范JGJ33-200134建筑施工扣件式钢管脚手架安全技术规范JGJ130-20115建筑施工安全检查标准JGJ59-20116北京市建筑工程施工安全操作...