南京至高淳新通道高淳陆岸段便桥施工组织设计南京至高淳新通道高淳陆岸段便桥(芦溪河便桥)指导性施工组织设计中交宁高新通道工程项目指挥部二0一三年一月1南京至高淳新通道高淳陆岸段便桥施工组织设计目录1编制说明................................................-4-1.1序言................................................-4-1.2编制依据............................................-4-2工程概况................................................-4-2.1工程项目特征........................................-4-2.1.1工程结构................................................-4-2.1.2主要技术指标............................................-4-2.1.3工程数量.................................................-5-2.2工程建设地点及环境特征..............................-5-2.2.1工程地质................................................-5-2.2.2水文条件................................................-6-2.3施工条件............................................-6-2.3.1水电设施................................................-6-2.3.2交通运输................................................-6-2.3.3通讯.....................................................-6-3施工准备及施工总体布置..................................-7-3.1总体策划............................................-7-3.1.1质量管理方针和质量管理目标...........................-7-3.1.2项目部机构设置.........................................-7-2南京至高淳新通道高淳陆岸段便桥施工组织设计3.2具体布置............................................-8-3.2.1施工准备工作计划.......................................-8-3.2.2施工进度计划...........................................-10-3.2.3资源需求计划...........................................-10-3.2.4施工平面图设计........................................-12-4施工方案综述...........................................-14-4.1主要结构尺寸.............................................-14-4.2总体施工方案.............................................-14-4.3施工工艺流程..............................................-15-5施工方案...............................................-16-5.1下部施工...........................................-16-5.1.1桩基础施工.............................................-16-5.1.2下横梁安装及桩顶处理..................................-17-5.2上部施工...........................................-17-5.2.1主梁及分配梁安装.......................................-17-5.2.2桥面板铺装及附属结构施工.............................-18-6施工技术组织措施.......................................-18-6.1质量保证措施.......................................-18-6.1.1技术措施...............................................-18-6.1.2管理措施...............................................-19-6.2职业健康安全保证措施...............................-22-3南京至高淳新通道高淳陆岸段便桥施工组织设计6.2.1建立安全保障体系......................................-22-6.2.2制定项目部安全危险源.................................-23-6.2.3狠抓安全法规、制度和安全操作规程的落实............-26-6.2.4事故应急救援预案......................................-26-6.2.5主要项目的施工安全技术措施..........................-29-6.3进度保证措施.......................................-34-6.3.1施工计划的保证........................................-34-6.3.2施工设备和材料的保证.................................-35-6.3.3人员的保证.............................................-35-6.3.4组织保证措施.....................