目录1.工程概况························31
1工程概况························31
2编制依据························31
3冲孔桩的施工说明····················41
4本工程要点·······················72.施工平面布置及施工用电、用水计划············82
1施工总平面布置·····················82
2临时设施的布置·····················82
3施工用水、用电计划···················83.项目管理机构及劳动力组织················83
1项目管理机构······················83
2劳动力配置计划·····················93
3拟投入本工程主要施工设备················104
施工进度计划及工期保证措施···············104
1施工进度计划······················104
2工期保证措施······················115
施工方案及施工方法···················125
1施工准备························125
2施工方法························145
3常见事故及处理措施···················215
4泥浆处理及渣土外运···················265
5冲孔灌注桩质量控制···················265
6工程质量检查验收····················286
质量保证体系及保证措施·················296
1质量保证体系···············