中铁四局集团第四工程有限公司架桥机安装与拆除施工安全专项方案扬州至绩溪高速公路广德至宁国段路基工程GN-04标架桥机安装与拆除施工安全专项方案编制:审核:审批:广德至宁国高速公路路基工程第四合同段中铁四局集团第四工程有限公司项目经理部二0一六年十一月二十日中铁四局集团第四工程有限公司架桥机安装与拆除施工安全专项方案目录一、编制依据·····························-1-二、编制目的·····························-1-三、编制原则·····························-2-1、安全第一的原则························-2-2、质量第一的原则························-2-3、科学配置的原则························-2-4、合理布局的原则························-2-二、工程概况·····························-2-1、工程概述···························-2-2、架桥机概述··························-3-三、架桥机主要结构··························-4-四、架桥机安装安全措施·······················-7-1、安装前的准备·························-7-2、安装场地···························-8-3、安装要求···························-8-4、安装、拆除人员的安排·····················-9-5、安装、拆除主要机具配备····················-9-6、安装顺序及施工组织······················-10-7、安装·····························-11-五、试运行和自检··························-14-1、架桥机试运行前的检查·····················-15-2、试运行检查··························-16-六、架桥机拆除安全措施·······················-16-1、拆除前的准备·························-16-2、拆除场地···························-16-3、拆除要求···························-17-4、拆除顺序及施工组织······················-17-七、维护保养····························-18-1、金属结构的维护保养······················-18-2、主要部件的维护保养······················-19-3、电器设备的维护保养······················-19-八、安全生产目标及方针·······················-20-中铁四局集团第四工程有限公司架桥机安装与拆除施工安全专项方案1、安全目标···························-20-2、安全方针···························-20-九、安全保证措施··························-20-1、安全保证体系及保障体系框图··················-20-2、安全管理组织机构及具体现场岗位职责分工············-21-十、安全保证制度··························-25-1、建立健全各项安全制度·····················-25-2、安全生产责任制························-25-3、安全生产应急管理制度·····················-26-4、三阶段风险分析与预防制度···················-27-十一、应急预案·······...