佛山市南海区西樵镇听音湖片区C-2地块观心山居项目工程给排水施工组织设计方案佛山南海区观心山居项目建筑给排水工程施工方案编制单位:广东电白建设集团有限公司编制日期:二0一七年二月九日目录1.编制依据................................................................3广东电白建设集团有限公司-0-C-2地块佛山市南海区西樵镇听音湖片区观心山居项目工程给排水施工组织设计方案1.1编制说明.............................................................31.2编制依据.............................................................42.工程概况................................................................42.1设计概况.............................................................42.2工程重点难点.........................................................62.3特别重要工序、关键工序、特殊工序的识别及措施.........................62.4创优目标.............................................................82.5创优方针.............................................................83.施工部署................................................................93.1施工组织.............................................................93.2施工部署原则.........................................................93.3现场组织协调........................................................103.4专业交叉作业安排....................................................133.5材料运输及管理......................................................144.主要工程量.............................................................145.施工准备...............................................................155.1技术准备............................................................155.2现场准备............................................................155.3材料准备............................................................165.4施工用具............................................................165.5人员配备............................................................176.施工方法...............................................................176.1安装准备............................................................176.2支吊架制作、安装....................................................176.3UPVC雨水管、HDPE双壁波纹管排水管安装...............................186.4钢塑复合给水管道安装施工工法........................................206.5阀门安装............................................................236.6水压试验............................................................246.7管道冲洗和消毒......................................................246.8设备安装............................................................257.质量保证体系及措施.....................................................287.1质量目标............................................................287.2质量保证体系........................................................287.3项目部质量保证体系图................................................307.4质量保证措施........................................................318.安全保证体系及措施.....................................................328.1安全管理目标........................................................328.2安全保证措施........................................................328.3文明施工保证措施....................................................349.进度计划及保证措施。...................................................359.1工程进度计划..........................