发放编号:003文件编号:08-001-QXHG山东潍坊泉鑫化工10000t/aYH高效油田化学品项目安装工程施工组织设计编制单位:山东建设第三安装工程有限公司潍坊泉鑫化工项目部审批单位:批准日期:山东潍坊泉鑫化工10000t/aYH高效油田化学品项目安装工程施工组织设计主编人:参加编制人员:部门会签:审核:审定:批准:山东建设第三安装工程有限公司2008年7月20日目录1.编制依据及原则..........................................................................................................................................21.1编制依据...........................................................................................................................................21.2编制原则...........................................................................................................................................21.3编制范围...........................................................................................................................................22.工程概况...................................................................................................................................................32.1施工条件...........................................................................................................................................32.2工程特点...........................................................................................................................................32.3施工范围...........................................................................................................................................33.施工顺序及工程进度安排.......................................................................................................................33.1施工顺序...........................................................................................................................................34.主要施工方法及技术措施.........................................................................................................................44.1施工作业指导书编制计划(见表4-1).........................................................................................44.3机械设备安装...................................................................................................................................54.4管道安装.........................................................................................................................................114.5电气安装.........................................................................................................................................144.6仪表安装.........................................................................................................................................184.7焊接工程.........................................................................................................................................255.劳动力、材料、施工机具安排...............................................................................................................275.1劳动力需求计划..........................................................................................................................275.2主要施工机具、设备配置计划.....................................................................................................275.3主要工程材料供应计划............................