大沙河河口水闸工程钢闸门吊装施工方案编制单位:深圳市骏基建设工程有限公司编制:审核:审批:编制日期:二○○八年十月十八日目录一、工程概述........................................................................................................................21.1编制依据..................................................................................................................21.2吊装简述..................................................................................................................21.3拟投入的施工机具..................................................................................................3二、吊装准备........................................................................................................................42.1施工准备..................................................................................................................4三、吊装作业........................................................................................................................53.1卸车..........................................................................................................................53.2将闸门转吊到闸槽工作位置...............................................................................63.3施工周期及准备......................................................................................................6四、质量目标与质量保证措施............................................................................................64.1质量目标.................................................................................................................64.2质量保证措施.........................................................................................................74.3质量保证体系..........................................................................................................7五、起重吊装的指挥和吊装工艺岗位的分工....................................................................815.1起重吊装的指挥协调工作......................................................................................8六、吊装工作应注意的安全事项........................................................................................9七、大件吊装工程危害辩识、评价控制措施表..............................................................10八、劳动力使用计划..........................................................................................................11九、应急预案......................................................................................................................129.1组织机构................................................................................................................129.2应急准备................................................................................................................129.3应急响应................................................................................................................12十、附录..............................................................................................................................13附录1、120吨汽车起重机性能表.............................................................................13附录2、起重机的选择与计算....................................................................................13附录3、吊装用钢丝绳受力计算及选择.........