苏州港常熟港区金泾塘作业区大新华通用件杂码头工程施工组织设计施工组织设计工程名称:苏州港常熟港区金泾塘作业区大新华通用件杂码头工程审批单位:中交第二航务工程局编制单位:中交第二航务工程局有限公司第四工程有限公司常熟港区金泾塘区大新华码头工程项目经理部技术负责人:技术负责人:审批者:编制者:审批日期:编制日期:二〇一二年四月中交第二航务工程局有限公司常熟港区金泾塘区大新华码头工程项目经理部1苏州港常熟港区金泾塘作业区大新华通用件杂码头工程施工组织设计目录第一章编制及施工依据···········································4第二章工程概况··················································52.1工程概述······················································52.2自然条件······················································82.3现场条件······················································142.4主要工程量····················································14第三章项目管理目标、方针、指标·······························173.1工期目标······················································173.2质量目标······················································183.3质量指标······················································183.4安全目标······················································183.5文明施工目标··················································183.6管理方针······················································19中交第二航务工程局有限公司常熟港区金泾塘区大新华码头工程项目经理部2苏州港常熟港区金泾塘作业区大新华通用件杂码头工程施工组织设计第四章施工总体部署··············································204.1施工总平面布置及临时设施······································204.2资源配置及进度计划············································234.2.1组织机构图··················································234.2.2管理体系布置················································244.2.3智能分配及职责··············································244.2.4各类人员配备表··············································324.2.5主要船机设备配备及需求计划··································334.2.6主要材料使用及供应计划······································354.2.7施工总体计划和关键节点计划··································36第五章主要工程项目施工工艺和方法·····························375.1施工方法的一般描述············...