目 录 一、编制依据 ··········································2二、工程概况 ··········································2三、工程重点及难点分析 ································3四、施工部署 ··········································3五、施工工艺流程 ······································5六、施工准备 ··········································6七、施工方案的选择 ····································7八、主要施工方法 ······································10九、质量保证措施 ······································24十、安全保证措施 ······································26十一、进度保证措施 ····································28十二、工程质量检验与验收······························28十三、基础工程检验批划分及试验检验····················29十四、成品保护措施 ····································30一、编制依据(一)、万科河运校项目一期基础施工图。(二)、勘察院提供的《万科河运校项目一期地质详勘报告》为依据。(三)、万科河运校项目一期规划局提供的测量放线成果图。(四)、国家现行工程质量验收标准及施工验收规范。二、工程概况(一)地质概况拟建场地平面上呈近似正方形,属剥蚀残丘斜坡地貌,原属重庆交通大学(大坪校区),场地现状东北部及中部水塘处地势低,标高约为 305.5~309.0m;场地西南部及东南部地势较低,标高约为 311.0m;场地北部及西部地势高,标高约为 315.0~320.0m;整体地势高差约 14.5m。(二)场地概况场地平基完成后形成两个台阶:北侧为-1 层,平基标高 313.7m,平基完成后大部分基岩裸露。南侧为-2 层,平基标高 310.4m,平基完成后大部分仍为土层覆盖,最大土层深度约 8m。北...