2009 年上半年系统集成项目管理工程师考试试题 [2009 年上半年上午题] ● Which of the following statement related to PMO is not correct? (71) (71) A. The specific form, function, and structure of a PMO is dependent upon the needs of the organization that it supports. B. One of the key features of a PMO is managing shared resources across all projects administered by the PMO. C. The PMO focuses on the specified project objectives. D. The PMO optimizes the use of shared organizational resources across all projects. [答案 C] [2009 年上半年上午题] ● The inputs of developing project management plan do not include (72). (72) A. project charter B. stakeholder management strategy C. project scope statement D. outputs from planning processes [答案 B] [2009 年上半年上午题] ● A project life cycle is a collection of generally sequential project (73)whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74)for managing the project, regardless of the specific work involved. (73)A. phases B. processes C. segments D. pieces (74)A. plan B. fraction C. main D. framework [答案 A、D] [2009 年上半年上午题] ● (75)is one of the quality planning outputs. (75) A. Scope base line B. Cost of quality C. Product specification D. Quality checklist [答案 D] 2009 年下半年系统集成项目管理工程师考试试题 69. 71.Ris kmanagement allows the project menaget and the project team not to (71) 。 (1.03 分) A.eliminate most risks durin gthe planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses .标准答案:A 70. 72.The project life-cycle can be described as (72) 。...