2009 年上半年系统集成项目管理工程师考试试题 [2009 年上半年上午题] ● Which of the following statement related to PMO is not correct
(71) (71) A
The specific form, function, and structure of a PMO is dependent upon the needs of the organization that it supports
One of the key features of a PMO is managing shared resources across all projects administered by the PMO
The PMO focuses on the specified project objectives
The PMO optimizes the use of shared organizational resources across all projects
[答案 C] [2009 年上半年上午题] ● The inputs of developing project management plan do not include (72)
(72) A
project charter B
stakeholder management strategy C
project scope statement D
outputs from planning processes [答案 B] [2009 年上半年上午题] ● A project life cycle is a collection of generally sequential project (73)