下载后可任意编辑目 录一、施工概述........................................................2二、施工管理........................................................2三、冬季施工措施....................................................3 3.1 钢筋及骨架的焊接............................................3 3.2 混凝土施工..................................................4 3.3 施工用水管道改造............................................53.4 砂石料存放..................................................53.5 拌合站保温..................................................53.6 拌和用水....................................................63.7 混凝土拌制..................................................63.8 混凝土运输..................................................63.9 混凝土浇筑..................................................63.10 结构物的保温措施...........................................7四、冬季施工质量、安全、消防保卫措施...............................104.1 混凝土质量控制及检查.......................................104.2 安全与防火.................................................10新仁街二号桥冬季施工方案新仁街二号桥因施工环境等诸多因素,根据现场实际情况,为确保按期完成工程建设任务,我部需要在冬季施工,拼抢关键工作面,特制定冬季施工方案。一、施工概述冬季施工因施工分项工程不同,要求有所不同。冬季施工的起止日期为:当冬天到来时,如连续五天的平均气温稳定在 5℃以下,则此 5d 的第一天未进入冬季施工的初日,当气温转暖时,最后一个5d 的日平均气温稳定在 5℃以上,则此 5d 的最后一天为冬季施工的终日。(日平均气温是 1d 内的 2、8、14 和 20 时等 4 次室外气温观测结果的平均值,这是在地面以上 1.5m 处,并远离热源的地方测得的)。根据往年气温情况,一般在 11 月至第二年 2 月期间实行冬季施工。根据我合同工程进展及工期要求,需要冬季施工的项目有承台、台身、现浇空心板梁。二、施工管理:1、成立以项目经理 李四平 为组长, 胡会军 为副组长的冬期施工领导组。冬施小组成员见下表: 中国核工业第二二建设有限公司铜仁教育园区技术部 1/12下载后可任意编辑序号姓 名分 工1李四平全面负责2...